June 16, 2015

New Mosaic Stadium One Year Construction Anniversary

New Mosaic Stadium Construction Facts 

  

  • To date over 25,500 cubic meters of concrete has been placed within the stadium.  At completion the amount of concrete placed would construct six office towers.
  • Over 410,000 hours have been worked on the site by the PCL construction team.
  • Currently 290 workers are on site, with an anticipated peak of 350 by this August.
  • More than 80 per cent of the excavated material has been removed from the site which equals 250,000 cubic metres.
  • New Mosaic Stadium will have nine elevators, compared to one in the current stadium. 
  • The total square footage of new Mosaic Stadium will be 521,866 which is more than double the existing stadium.
  • The field of play will be 10.547m below grade.
  • When complete the height from the field of play to the highest point in the roof will be 55.606 meters.


Check out this rendered image of the Harvard General Admission Lounge.  

 

For more updated images and information go to newmosaicstadium.com